A hole appeared in mid-October in an area of
public open space adjacent to No. 30 Highbarns and arrangements
made for geotechnical engineers to visit the site.
The collapse has revealed a brick shaft approximately 1.2m in
diameter that appears to be a former well.
Land close to this area has had stabilisation works carried out to
it over the past decade.
Intrusive ground investigation work was carried out around the
collapse feature to ascertain the extent of the sub-surface and
loosened ground to enable the design of remedial works.
Initial results of the dynamic probing has identified a void
running from the edge of the collapsed feature towards No. 30 East
Green, and the rough scope of this void has been identified as
being approximately 13.5 m x 4 m.
Cabinet have agreed to the use of the Dacorum Development Reserve
to fund the remediation works.
Cabinet have delegated authority to award a contract for the
remediation work to the Assistant Director Corporate.
Decision type: Non-key
Decision status: Recommendations Approved
Notice of proposed decision first published: 07/07/2021
Decision due: 23 Jun 2021 by Assistant Director - Legal and Democratic Services
Contact: Ben Hosier, Head of Commercial Development 01442 228215 Email: ben.hosier@dacorum.gov.uk Email: ben.hosier@dacorum.gov.uk.