Minutes:
J Gardner introduced the item and said it had been referred to the committee as the land is currently owned by Dacorum Borough Council.
Patrick O’Sullivan spoke in support of the application.
It was proposed by Councillor C Wyatt-Lowe and seconded by Councillor Birnie to grant the application in line with the officer’s recommendation.
Vote
For: 10 Against: 0 Abstained: 0
Resolved:
That planning permission be DELEGATED with a view to grant subject to completion of a S.106 agreement and the following conditions:
1 |
The development hereby permitted shall be begun before the expiration of three years from the date of this permission.
Reason: To comply with the requirements of Section 91 (1) of the Town and Country Planning Act 1990 as amended by Section 51 (1) of the Planning and Compulsory Purchase Act 2004. |
2 |
The development hereby permitted shall be carried out in accordance with the following approved plans/documents:
ALP004 APL006 APL007 APL008 ALP009 ALP010 ALP011 ALP012 ALP013 APL014 APL015 ALP017 ALP018 Development Site Impact Assessment & Method Statement (Bartlett Consulting) Date: Thursday 12th October 2017
Reason: For the avoidance of doubt and in the interests of proper planning. |
3 |
The development hereby permitted shall be constructed in accordance with the materials specified on the approved drawings or such other materials as may be agreed in writing by the local planning authority.
Reason: To ensure a satisfactory appearance to the development.
|
4 |
The development permitted by this planning permission shall be carried out in accordance with the approved The Drainage and SuDS Strategy carried out by Price & Myers reference 26156 Rev 2 dated August 2017 and supporting information submitted and the following mitigation measures detailed within the FRA:
· Implement appropriate drainage strategy based on attenuation and discharge into Thames Surface water sewer. · Limiting the surface water run-off to a maximum of 3l/s generated by the 1 in 100 year + climate change critical storm so that it will not exceed the run-off from the undeveloped site and not increase the risk of flooding off-site. · Implement drainage strategy utilising permeable paving and attenuation tank.
Reason: To reduce the risk of flooding to the proposed development and future occupants. |
5 |
No development shall take place until the final design of the drainage scheme is completed and sent to the LPA for approval. The scheme shall also include:
· Detailed engineered drawings of the proposed SuDS features including their location, size, volume, depth and any inlet and outlet features including any connecting pipe runs and all corresponding calculation. · Final design should incorporate silt traps and appropriate pollution prevention methods to ensure surface water run-off from the proposed car parking and roads can be treated in a sustainable manner and reduce the requirement for maintenance of underground features. · Detailed surface water calculations for all rainfall events up to and including the 1 in 100 year + climate change event supported by a clearly labelled drainage layout plan showing pipe networks. This plan should show any pipe 'node numbers' that have been referred to in network calculations and it should also show invert and cover levels of manholes.
Reason: To prevent flooding by ensuring the satisfactory storage of and disposal of surface water from the site. |
6 |
Upon completion of the drainage works an updated management and maintenance plan for all the SuDS features and structure must be submitted and shall include arrangements for adoption and any other arrangements to secure the operation of the scheme throughout its lifetime.
Reason: To prevent the increased risk of flooding. |
7 |
Prior to the commencement of the development hereby permitted a Phase I Report to assess the actual or potential contamination at the site shall be submitted to and approved in writing by the local planning authority. If actual or potential contamination and/or ground gas risks are identified further investigation shall be carried out and a Phase II report shall be submitted to and approved in writing by the local planning authority prior to the commencement of the development. If the Phase II report establishes that remediation or protection measures are necessary a Remediation Statement shall be submitted to and approved in writing by the Local Planning Authority. For the purposes of this condition: A Phase I Report consists of a desk study, site walkover, conceptual model and a preliminary risk assessment. The desk study comprises a search of available information and historical maps which can be used to identify the likelihood of contamination. A simple walkover survey of the site is conducted to identify pollution linkages not obvious from desk studies. Using the information gathered, a ‘conceptual model’ of the site is constructed and a preliminary risk assessment is carried out. A Phase II Report consists of an intrusive site investigation and risk assessment. The report should make recommendations for further investigation and assessment where required. A Remediation Statement details actions to be carried out and timescales so that contamination no longer presents a risk to site users, property, the environment or ecological systems. Reason: To ensure that the issue of contamination is adequately addressed and to ensure a satisfactory development. |
8 |
All remediation or protection measures identified in the Remediation Statement referred to in Condition 7 shall be fully implemented within the timescales and by the deadlines as set out in the Remediation Statement and a Site Completion Report shall be submitted to and approved in writing by the local planning authority prior to the first occupation of any part of the development hereby permitted. For the purposes of this condition a Site Completion Report shall record all the investigation and remedial or protection actions carried out. It shall detail all conclusions and actions taken at each stage of the works including validation work. It shall contain quality assurance and validation results providing evidence that the site has been remediated to a standard suitable for the approved use.
Reason: To ensure that the issue of contamination is adequately addressed and to ensure a satisfactory development. |
9 |
In this condition "retained tree" means an existing tree which is to be retained in accordance with the approved plans and particulars; and paragraphs (a) and (b) below shall have effect until the expiration of [1 year] from the date of the occupation of the building for its permitted use.
(a) No retained tree shall be cut down, uprooted or destroyed, nor shall any retained tree be topped or lopped other than in accordance with the approved plans and particulars, without the written approval of the local planning authority. Any topping or lopping approved shall be carried out in accordance with British Standard 3998: 1989 Recommendations for Tree Work.
(b) If any retained tree is removed, uprooted or destroyed or dies, another tree shall be planted at the same place and that tree shall be of such size and species, and shall be planted at such time, as may be specified in writing by the local planning authority.
(c) The erection of fencing and other ground protection measures for the protection of any retained tree shall be undertaken in accordance with the approved plans and particulars before any equipment, machinery or materials are brought on to the site for the purposes of the development, and shall be maintained until all equipment, machinery and surplus materials have been removed from the site. Nothing shall be stored or placed in any area fenced in accordance with this condition and the ground levels within those areas shall not be altered, nor shall any excavation be made, without the written consent of the local planning authority.
Reason: To ensure a satisfactory appearance to the development and to safeguard the visual character of the immediate area. |
10 |
No materials, plant, soil or spoil shall be stored underneath the canopy of any tree on the site which is shown for retention on the approved Drawing No. APL004
Reason: In order to ensure that damage does not occur to the trees during building operations.
Article 35 Statement
Planning permission has been granted for this proposal. The Council acted pro-actively through early engagement with the applicant at the pre-application stage which lead to improvements to the scheme. The Council has therefore acted pro-actively in line with the requirements of the Framework (paragraphs 186 and 187) and in accordance with the Town and Country Planning (Development Management Procedure) (England) (Amendment No. 2) Order 2015.
INFORMATIVES AN1) Where works are required within the public highway to facilitate the new vehicle access, the Highway Authority require the construction of such works to be undertaken to their satisfaction and specification, and by a contractor who is authorised to work in the public highway. Before works commence the applicant will need to apply to Hertfordshire County Council Highways team to obtain their permission and requirements. Their address is County Hall, Pegs Lane, Hertford, Herts, SG13 8DN. Their telephone number is 0300 1234047. AN2) Storage of materials, site parking and deliveries: The applicant is advised that the storage of materials associated with the construction of this development should be provided within the site on land which is not public highway, and the use of such areas must not interfere with the public highway. On-site parking for all contractors, sub-contractors, visitors and delivery shall also be off the highway. If this is not possible, authorisation should be sought from the Highway Authority before construction works commence. Further information is available via the website http://www.hertsdirect.org/services/transtreets/highways/ or by telephoning 0300 1234047. AN3) Road Deposits: It is an offence under section 148 of the Highways Act 1980 to deposit mud or other debris on the public highway, and section 149 of the same Act gives the Highway Authority powers to remove such material at the expense of the party responsible. Therefore, best practical means shall be taken at all times to ensure that all vehicles leaving the site during construction of the development are in a condition such as not to emit dust or deposit mud, slurry or other debris on the highway. Further information is available via the website http://www.hertsdirect.org/services/transtreets/highways/ or by telephoning 0300 1234047.
Paragraph 121 of the NPPF states that all site investigation information must be prepared by a competent person. This is defined in the framework as ‘A person with a recognised relevant qualification, sufficient experience in dealing with the type(s) of pollution or land instability, and membership of a relevant professional organisation.’ Contaminated Land Planning Guidance can be obtained from Regulatory Services or via the Council’s website www.dacorum.gov.uk
|
Supporting documents: