Agenda item

4/02881/16/FUL - INSTALLATION OF 5 NEW PARKING BAYS ON AMENITY GREEN - CRANFORD, FLETCHER WAY, HEMEL HEMPSTEAD, HP2 5QP

Minutes:

M Heron introduced the item and said it had been referred to committee as Dacorum Borough Council has an interest in land at the application site.

It was proposed by Councillor Birnie and seconded by Councillor Whitman to grant the application in line with the officer’s recommendation.

Vote

For: 12             Against: 0                    Abstained: 0

Resolved:

That planning permission be GRANTED subject to the following conditions:

1

The development hereby permitted shall be begun before the expiration of three years from the date of this permission.

 

Reason:  To comply with the requirements of Section 91 (1) of the Town and Country Planning Act 1990 as amended by Section 51 (1) of the Planning and Compulsory Purchase Act 2004.

 

2

The development hereby permitted shall not be carried out other than in accordance with the following approved plans/documents: DBC/016/012 (scale of 1:200).

 

Reason: For the avoidance of doubt, in the interests of proper planning and to ensure that the proposal is acceptable in terms of flooding and drainage, in accordance with Policies CS31 of the Dacorum Core Strategy 2013.

 

 

3

Prior to the construction of the parking spaces hereby approved, full specifications of the materials to be used for hardstandings shall be submitted to and approved in writing by the Local Planning Authority. Subsequently, the development shall be carried out and retained in accordance with approved details.

 

Reason: To ensure a satisfactory appearance to the development, in accordance with Policies CS11 and CS12 of the Dacorum Core Strategy 2013.

 

 

4

Prior to first use of the parking spaces hereby approved full details on a suitably scaled plan of soft landscape works must be submitted to and approved in writing by the Local Planning Authority. Subsequently, these works shall be in addition to those shown on the approved plans and shall be carried out and retained as approved.  The landscaping details to be submitted shall include:-

 

a) planting plans for replacement trees, including specifications of species, sizes, planting centres, planting method and number and percentage mix;

 

Reason: The landscaping of this site is required in order to protect and enhance the existing visual character of the area and to reduce the visual and environmental impacts of the development hereby permitted in accordance with Policies 99 and 100 of the Dacorum Local Plan 2004.

 

5

All planting, seeding or turfing and soil preparation comprised in the approved details of landscaping shall be carried out in the first planting and seeding seasons following first occupation of the building; and any trees or plants which within a period of five years from the completion of the development die, are removed or become seriously damaged or diseased shall be replaced in the next planting season with others of similar size and species, unless the Local Planning Authority gives written approval to any variation. All landscape works shall be carried out in accordance with the guidance contained in British Standards unless otherwise agreed in writing by the Local Planning Authority.

 

Reason: To ensure proper implementation of the agreed landscape details in the interest of the amenity value of the development in accordance with Policies 99 and 100 of the Dacorum Local Plan 2004.

 

Planning permission has been granted for this proposal. Discussion with the applicant to seek an acceptable solution was not necessary in this instance. The Council has therefore acted pro-actively in line with the requirements of the Framework (paragraphs 186 and 187) and in accordance with the Town and Country Planning (Development Management Procedure) (England) Order 2015.  

 

Informatives:

 

1. Storage of materials: The applicant is advised that the storage of materials associated with the construction of this development should be provided within the site on land which is not public highway, and the use of such areas must not interfere with the public highway. If this is not possible, authorisation should be sought from the Highway Authority before construction works commence. Further information is available via the website http://www.hertsdirect.org/services/transtreets/highways/ or by telephoning 0300 1234047.

 

2. Obstruction of public highway land: It is an offence under section 137 of the Highways Act 1980 for any person, without lawful authority or excuse, in any way to wilfully obstruct the free passage along a highway or public right of way. If this development is likely to result in the public highway or public right of way network becoming routinely blocked (fully or partly) the applicant must contact the Highway Authority to obtain their permission and requirements before construction works commence. Further information is available via the website http://www.hertsdirect.org/services/transtreets/highways/ or by telephoning 0300 1234047.

 

 