5d. 22/02770/FUL
Erection of a 3 bedroom dwelling
2 Coniston Road, Kings Langley, Hertfordshire, WD4 8BU
The Case OfficerSally Robbins, introduced the report to Members and said that the application had been referred to the Committee due to contrary views of Parish Council.
It was proposed by Councillor Durrant and seconded by Councillor Beauchamp to DELEGATED with a view to APPROVAL in line with Officers recommendations.
Vote:
For: 10 Against: 1 Abstained: 1
Resolved: That planning permission be DELEGATED with a view to APPROVAL.
That the application be DELEGATED with a view to APPROVAL subject to appropriate assessment in accordance with article 6(3) of the Habitats Directive and securing a mitigation package to avoid any further significant effects on the Chilterns Beechwood Special Area of Conservation (SAC) through financial contributions secured by legal agreement.
Conditions and Reasons:
1. The development hereby permitted shall begin before the expiration of three years from the date of this permission.
Reason: To comply with the requirements of Section 91 (1) of the Town and Country Planning Act 1990, as amended by Section 51 (1) of the Planning and Compulsory Purchase Act 2004.
2. No development (excluding demolition/ground investigations) shall take place until details of the materials to be used in the construction of the external surfaces of the development hereby permitted have been submitted and approved in writing by the Local Planning Authority. Development shall be carried out in accordance with the approved details.
Reason: To ensure satisfactory appearance to the development and to safeguard the visual character of the area in accordance with Policies CS11 and CS12 of the Dacorum Borough Core Strategy (2013).
3. No construction of the superstructure shall take place until full details of both hard and soft landscape works has been submitted to and approved in writing by the Local Planning Authority. These details shall include:
a) all external hard surfaces within the site
b) soft landscape works, including a planting scheme with the number, size, species and position of trees, plants and shrubs.
The planting must be carried out within one planting season of completing the development.
Any tree or shrub which forms part of the approved landscaping scheme which within a period of 5 years from planting fails to become established, becomes seriously damaged or diseased, dies or for any reason is removed shall be replaced in the next planting season by a tree or shrub of a similar species, size and maturity.
Reason: To improve the appearance of the development and its contribution to biodiversity and the local environment, as required by saved Policy 99 of the Dacorum Borough Local Plan (2004) and Policy CS12 (e) of the Dacorum Borough Council Core Strategy (2013).
4. The new dwelling hereby approved shall not be occupied until the new vehicular access shown on drawing number 'PL004 Rev A' has been completed in accordance with details/specifications to be submitted to and approved in writing by the Local Planning Authority in consultation with the Highway Authority. The vehicular access shall thereafter be retained for the use of the dwelling known as 2 Coniston Road. Prior to the occupation of the dwelling hereby approved, appropriate arrangements shall be made for surface water to be intercepted and disposed of separately so that it does not discharge from or onto the highway carriageway.
Reason: To ensure satisfactory access into the site and avoid carriage of extraneous material or surface water from or onto the highway, in accordance with Dacorum Borough Core Strategy (2013) Policies CS8 and CS12.
5. Notwithstanding the provisions of the Town and Country Planning (General Permitted Development) Order 2015 (as amended) (or any Order amending or re-enacting that Order with or without modification) no windows, dormer windows, doors or other openings other than those expressly authorised by this permission shall be constructed without the prior written approval of the local planning authority.
Reason: To protect the residential amenities of the locality, having regard to Policy CS12 of the Dacorum Borough Core Strategy (2013) and Paragraph 130 (f) of the National Planning Policy Framework (2021).
6. The development hereby permitted shall be carried out in accordance with the following approved plans/documents:
Planning Statement
PL/001 - Location & Site Plan
PL/002 - Proposed Plans
PL/003 Rev A - Proposed Elevations
PL/004 Rev A - Crossover Details
Reason: For the avoidance of doubt and in the interests of proper planning.
Informatives:
1. New or amended vehicle crossover access (section 184): Where works are required within the public highway to facilitate a new or amended vehicular access, the Highway Authority require the construction of such works to be undertaken to their satisfaction and specification, and by a contractor who is authorised to work in the public highway. If any of the works associated with the construction of the access affects or requires the removal and/or the relocation of any equipment, apparatus or structures (e.g. street name plates, bus stop signs or shelters, statutory authority equipment etc.) the applicant will be required to bear the cost of such removal or alteration.
Before works commence the applicant will need to apply to the Highway Authority to obtain their permission, requirements and for the work to be carried out on the applicant's behalf. Further information is available via the County Council website at:
https://www.hertfordshire.gov.uk/services/highways-roads-and-pavements/changes-to-your-road/dropped-kerbs/dropped-kerbs.aspx or by telephoning 0300 1234047.
2. Storage of materials: The applicant is advised that the storage of materials associated with the construction of this development should be provided within the site on land which is not public highway, and the use of such areas must not interfere with the public highway. If this is not possible, authorisation should be sought from the Highway Authority before construction works commence. Further information is available via the County Council website at:
https://www.hertfordshire.gov.uk/services/highways-roads-and-pavements/business-and-developer-information/business-licences/business-licences.aspx or by telephoning 0300 1234047.
3. Obstruction of highway: It is an offence under section 137 of the Highways Act 1980 for any person, without lawful authority or excuse, in any way to wilfully obstruct the free passage along a highway or public right of way. If this development is likely to result in the public highway or public right of way network becoming routinely blocked (fully or partly) the applicant must contact the Highway Authority to obtain their permission and requirements before construction works commence. Further information is available via the County Council website at:
https://www.hertfordshire.gov.uk/services/highways-roads-and-pavements/business-and-developer-information/business-licences/business-licences.aspx or by telephoning 0300 1234047.
4. Debris and deposits on the highway: It is an offence under section 148 of the Highways Act 1980 to deposit compost, dung or other material for dressing land, or any rubbish on a made up carriageway, or any or other debris on a highway to the interruption of any highway user. Section 149 of the same Act gives the Highway Authority powers to remove such material at the expense of the party responsible. Therefore, best practical means shall be taken at all times to ensure that all vehicles leaving the site during construction of the development and use thereafter are in a condition such as not to emit dust or deposit mud, slurry or other debris on the highway. Further information is available by telephoning 0300 1234047.
5. Working Hours: Contractors and sub-contractors must have regard to BS 5228-2:2009 "Code of Practice for Noise Control on Construction and Open Sites" and the Control of Pollution Act 1974.
As a guideline, the following hours for noisy works and/or deliveries should be observed: Monday to Friday, 7.30am to 5:30pm, Saturday, 8am to 1pm, Sunday and bank holidays - no noisy work allowed.
Where permission is sought for works to be carried out outside the hours stated, applications in writing must be made with at least seven days' notice to Environmental and Community Protection Team ecp@dacorum.gov.uk or The Forum, Marlowes, Hemel Hempstead, HP1 1DN. Local residents that may be affected by the work shall also be notified in writing, after approval is received from the LPA or Environmental Health.
Works audible at the site boundary outside these hours may result in the service of a Notice restricting the hours as above. Breach of the notice may result in prosecution and an unlimited fine and/or six months imprisonment.
6. Construction Dust: Dust from operations on the site should be minimised by spraying with water or by carrying out of other such works that may be necessary to supress dust. Visual monitoring of dust is to be carried out continuously and Best Practical Means (BPM) should be used at all times. The applicant is advised to consider the control of dust and emissions from construction and demolition Best Practice Guidance, produced in partnership by the Greater London Authority and London Councils.
7. Waste Management: Under no circumstances should waste produced from construction work be incinerated on site. This includes but is not limited to pallet stretch wrap, used bulk bags, building materials, product of demolition and so on. Suitable waste management should be in place to reduce, reuse, recover or recycle waste product on site, or dispose of appropriately.
8. Air Quality: As an authority we are looking for all development to support sustainable travel and air quality improvements as required by the NPPF. We are looking to minimise the cumulative impact on local air quality that ongoing development has, rather than looking at significance. This is also being encouraged by DEFRA.
As a result as part of the planning application I would recommend that the applicant be asked to propose what measures they can take as part of this new development, to support sustainable travel and air quality improvements. These measures may be conditioned through the planning consent if the proposals are acceptable.
A key theme of the NPPF is that developments should enable future occupiers to make "green" vehicle choices and (paragraph 35) "incorporates facilities for charging plug-in and other ultra-low emission vehicles". Therefore an electric vehicle recharging provision rate of 1 vehicle charging point per 10 spaces (unallocated parking) is expected. To prepare for increased demand in future years, appropriate cable provision should be included in the scheme design and development, in agreement with the local authority.
Please note that with regard to EV charging for residential units with dedicated parking, we are not talking about physical charging points in all units but the capacity to install one. The cost of installing appropriate trunking/ducting and a dedicated fuse at the point of build is miniscule, compared to the cost of retrofitting an EV charging unit after the fact, without the relevant base work in place.
In addition, mitigation in regards to NOx emissions should be addressed in that all gas fired boilers to meet a minimum standard of 40 mg NOx/Kwh or consideration of alternative heat sources.
9. Invasive and Injurious Weeds: Weeds such as Japanese Knotweed, Giant Hogsweed and Ragwort are having a detrimental impact on our environment and may injure livestock. Land owners must not plant or otherwise cause to grow in the wild any plant listed on schedule 9 of the Wildlife and Countryside Act 1981. Developers and land owners should therefore undertake an invasive weeds survey before development commences and take the steps necessary to avoid weed spread. Further advice can be obtained from the Environment Agency website at https://www.gov.uk/japanese-knotweed-giant-hogweed-and-other-invasive-plants.
10. Contaminated Land Informative 1: In the event that contamination is found at any time when carrying out the approved development it must be reported in writing immediately to the Local Planning Authority with all works temporarily suspended until a remediation method statement has been agreed. This is because the safe development and secure occupancy of the site lies with the developer.
11. Contaminated Land Informative 2: Materials or conditions that may be encountered at the site and which could indicate the presence of contamination include, but are not limited to: Soils that are malodorous, for example a fuel odour or solvent-type odour, discoloured soils, soils containing man-made objects such as paint cans, oil/chemical drums, vehicle or machinery parts etc., or fragments of asbestos or potentially asbestos containing materials. If any other material is encountered that causes doubt, or which is significantly different from the expected ground conditions advice should be sought.
12. Planning permission has been granted for this proposal. Discussion with the applicant to seek an acceptable solution was not necessary in this instance. The Council has therefore acted pro-actively in line with the requirements of the Framework (paragraph 38) and in accordance with the Town and Country Planning (Development Management Procedure) (England) (Amendment No. 2) Order 2015.