Minutes:
Cllr Douris declared an interest however was able to take part in the discussion and vote.
The report was introduced by the case officer Colin Lecart
It was proposed by Councillor Anderson and seconded by Councillor Williams that the application be Granted
Vote:
For: 8 against: 0 Abstained: 2
Resolved: Granted
Condition(s) and Reason(s):
1. The development hereby permitted shall begin before the expiration of three years from the date of this permission.
Reason: To comply with the requirements of Section 91 (1) of the Town and Country Planning Act 1990, as amended by Section 51 (1) of the Planning and Compulsory Purchase Act 2004.
2. The development hereby permitted shall be carried out in accordance with the following approved plans/documents:
3818-P1A
3818-L4G
Reason: For the avoidance of doubt and in the interests of proper planning.
3. The development hereby permitted shall be constructed in accordance with the materials specified on the application form.
Reason: To make sure that the appearance of the building is suitable and that it contributes to the character of the area in accordance with Policies CS11 and CS12 of the Dacorum Borough Core Strategy (2013).
4. Prior to the commencement of development hereby approved, an Arboricultural Method Statement and Tree Protection Plan prepared in accordance with BS5837:2012 (Trees in relation to design, demolition and construction) setting out how trees shown for retention shall be protected during the construction process, shall be submitted to and approved by the Local Planning Authority. No equipment, machinery or materials for the development shall be taken onto the site until these details have been approved. The works must then be carried out according to the approved details and thereafter retained until competition of the development.
Reason: In order to ensure that damage does not occur to trees and hedges during building operations in accordance with saved Policy 99 of the Dacorum Borough Local Plan (2004), Policy CS12 of the Dacorum Borough Core Strategy (2013) and Paragraph 174 of the National Planning Policy Framework (2021).
5. Notwithstanding the provisions of the Town and Country Planning (General Permitted Development) Order 2015 (as amended) (or any Order amending or re-enacting that Order with or without modification) no development falling within the following classes of the Order shall be carried out without the prior written approval of the Local Planning Authority:
Schedule 2, Part 2, Class A
Reason: To enable the Local Planning Authority to retain control over the development in the interests of safeguarding the visual amenity of the area as well as the openess of the Green Belt in accordance with Policy CS5 of the Dacorum Core Strategy (2013) and Policy 81 of the Dacorum Local Plan (2004).
Informatives:
1. Planning permission has been granted for this proposal. Discussion with the applicant to seek an acceptable solution was not necessary in this instance. The Council has therefore acted pro-actively in line with the requirements of the Framework (paragraph 38) and in accordance with the Town and Country Planning (Development Management Procedure) (England) (Amendment No. 2) Order 2015.
2. It is an offence under section 137 of the Highways Act 1980 for any person, without lawful authority or excuse, in any way to wilfully obstruct the free passage along a highway or public right of way. If this development is likely to result in the public highway or public right of way network becoming routinely blocked (fully or partly) the applicant must contact the Highway Authority to obtain their permission and requirements before construction works commence.
3. It is an offence under section 148 of the Highways Act 1980 to deposit mud or other debris on the public highway, and section 149 of the same Act gives the Highway Authority powers to remove such material at the expense of the party responsible. Therefore, best practical means shall be taken at all times to ensure that all vehicles leaving the site during construction of the development are in a condition such as not to emit dust or deposit mud, slurry or other debris on the highway.
4. The applicant is advised that the storage of materials associated with the construction of this development should be provided within the site on land which is not public highway, and the use of such areas must not interfere with the public highway. If this is not possible,
authorisation should be sought from the Highway Authority before construction works commence.