Issue - meetings

Eastwick Row Contractor Approval

Meeting: 30/01/2024 - Cabinet (Item 10)

10 Eastwick Row Contractor Approval pdf icon PDF 574 KB

Additional documents:

Decision:

Principal Contractor Appointment.

 

Cabinet:

 

1.         Approved entering into the JCT D&B contract with Bugler Developments Ltd for the delivery 34 units at Eastwick Row, Hemel Hempstead.

 

2.         Delegated authority to the Assistant Director (Legal & Democratic Services) to execute and complete all legal agreements ancillary to the JCT Design & Build Contract 2016 and/or reasonably required to complete the Project, including (but not limited to):

 

a.         all professional appointments;

b.         collateral warranties; and

c.         Agreements under

S.38, & S.278, of the Highways Act 1980;

S.247, Part III of the Town and Country Planning Act 1990;

S.104 of the Water Industry Act 1991, and

S.50 of the New Roads and Street Works Act 1991.

 

Minutes:

Decision

Principal Contractor Appointment.

 

That Cabinet:

 

1.      Approves entering into the JCT D&B contract with Bugler Developments Ltd for the delivery 34 units at Eastwick Row, Hemel Hempstead.

 

2.      Delegates authority to the Assistant Director (Legal & Democratic Services) to execute and complete all legal agreements ancillary to the JCT Design & Build Contract 2016 and/or reasonably required to complete the Project, including (but not limited to):

 

a.      all professional appointments;

b.      collateral warranties; and

c.      Agreements under

S.38, & S.278, of the Highways Act 1980;

S.247, Part III of the Town and Country Planning Act 1990;

S.104 of the Water Industry Act 1991, and

S.50 of the New Roads and Street Works Act 1991.

 

Advice

 

Recommendation agreed

 

Please refer to the video minutes to view this item in full.