Principal Contractor Appointment.
Cabinet:
1. Approved entering into the JCT D&B contract with Bugler Developments Ltd for the delivery 34 units at Eastwick Row, Hemel Hempstead.
2. Delegated authority to the Assistant Director (Legal & Democratic Services) to execute and complete all legal agreements ancillary to the JCT Design & Build Contract 2016 and/or reasonably required to complete the Project, including (but not limited to):
a. all professional appointments;
b. collateral warranties; and
c. Agreements under
S.38, & S.278, of the Highways Act 1980;
S.247, Part III of the Town and Country Planning Act 1990;
S.104 of the Water Industry Act 1991, and
S.50 of the New Roads and Street Works Act 1991.
Minutes:
Decision
Principal Contractor Appointment.
That Cabinet:
1. Approves entering into the JCT D&B contract with Bugler Developments Ltd for the delivery 34 units at Eastwick Row, Hemel Hempstead.
2. Delegates authority to the Assistant Director (Legal & Democratic Services) to execute and complete all legal agreements ancillary to the JCT Design & Build Contract 2016 and/or reasonably required to complete the Project, including (but not limited to):
a. all professional appointments;
b. collateral warranties; and
c. Agreements under
S.38, & S.278, of the Highways Act 1980;
S.247, Part III of the Town and Country Planning Act 1990;
S.104 of the Water Industry Act 1991, and
S.50 of the New Roads and Street Works Act 1991.