Decision Maker: Cabinet
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: Yes
Cabinet Agreed
1. That the main contract to construct 25 social rented units at five garage site locations in Hemel Hempstead and Kings Langley be awarded to Bugler Developments Limited.
2. That delegated authority be approved to the Council’s Assistant Director (Corporate and Contracted Services) to execute and complete all legal agreements ancillary to the JCT Design & Build Contract 2016 and/or reasonably required to complete the Project, including (but not limited to):
a. all professional appointments;
b. collateral warranties; and
c. Agreements under
S.38, & S.278, of the Highways Act 1980;
S.247, Part III of the Town and Country Planning Act
1990;
S.104 of the Water Industry Act 1991, and
S.50 of the New Roads and Street Works Act 1991.
Publication date: 20/12/2021
Date of decision: 14/12/2021
Decided at meeting: 14/12/2021 - Cabinet
Effective from: 28/12/2021