Approval to extend Hyas Associates Ltd contract to provide Hemel Garden Communities with external resource

Decision Maker: Assistant Director - Planning

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: No

Purpose:

A 6 month extension of Hyas Associates Ltd contract is to be approved to secure external programme resource to support the Hemel Garden Communities programme.

Decision:

Approved at commercial board 9th Feb.

Alternative options considered:

The direct award of the contract via a compliant framework agreement will ensure that the contract is compliant, and the client officer has confirmed that the costs from Hyas are comparative, but the benefit of continuing to work with Hyas from a consistency perspective is the main reason for the direct award.

Publication date: 13/03/2024

Date of decision: 12/03/2024